Oregon Community Solar Program
The Oregon Community Solar Program was first introduced through Oregon Administrative Rules (OAR) 860-088. This rule's creation was directed under 2016 Senate Bill 1547, with administrative authority being given to the Public Utility Commission. Community Solar projects may only be approved if ownership is demonstrated for 50 percent or more of project nameplate capacity. Additionally, community solar projects must have a subscription minimum of 5 persons and not exceed 3 megawatts in nameplate capacity. Projects must be located in the Oregon service territory of an electric utility, with at least 10 percent of the project generating capacity allocated exclusively