State affected: North Carolina
North Carolina has a real solar deadline on December 31, 2026 — and a capacity question sitting right next to it that no one can answer for you from a website. Duke Energy's Net Metering Bridge rate closes to new participants on January 1, 2027. If you want it, the thing that counts is a valid interconnection request filed with Duke by December 31 — not a signed sales contract, and not an installation. But the Bridge also has a yearly capacity cap, and Duke does not publish a live figure for how much of this year's room is left. That is the honest starting point: the date is certain, the room is not, and you should get both in writing before you sign anything.
This is the first SolarUSA News article devoted to North Carolina. The state has never had one of its own — only the installer directory and program pages. North Carolina solar installers can model both tariffs against your actual usage before you sign. If you want a price for a system in Duke territory, get a solar quote and ask the installer, in writing, for the interconnection filing date and the rider name the quote assumes.
Since October 1, 2023, a new Duke Energy rooftop customer in North Carolina has had two residential choices, both approved by the North Carolina Utilities Commission in March 2023 (Docket E-100, Sub 180) and summarised in our North Carolina net metering rules. The Net Metering Bridge (Rider NMB) is the simpler of the two: no time-of-use rate is required, your solar offsets your usage month to month, and leftover power at month's end earns the Net Excess Energy Credit — 4.53 cents per kWh in Duke Energy Carolinas territory and 3.94 cents in Duke Energy Progress territory. It also carries a monthly minimum bill ($22 in Carolinas, $28 in Progress) and a non-bypassable charge (about $1.01 per kW per month in Carolinas under the July 2026 tariff leaf; $1.16 in Progress), but no Grid Access Fee.
The Bridge closes to new participants on and after January 1, 2027. That wording comes from Duke's own tariff: Rider NMB for Duke Energy Carolinas (Fifth Revised Leaf No. 143, effective July 1, 2026) states plainly that the rider "will be closed to new participants on and after January 1, 2027." Once you are in, you can stay on it for up to 15 calendar years from the date of your interconnection application — not from the day the system turns on.
Under the Bridge tariff, enrollment is first come, first served, and a spot is reserved when a valid interconnection application is submitted. That is the point the tariff-based guides agree on, and it is the point that matters most for the deadline. A contract signed in December does not help if the interconnection request goes in after December 31, 2026, or after that year's room is used up. Your installer usually files that application, not you — so the filing date is a thing to get in writing, with a copy or screenshot of the submitted application, before you treat the Bridge as locked in.
Two cautions belong here. First, a few installer guides say instead that Duke must approve the interconnection before the spot is locked. The tariff language I checked says submission reserves the spot; I could not confirm the approval version on Duke's tariff pages, so do not take either version on trust — ask Duke or your installer for the trigger in writing for your account. Second, the Bridge has a yearly cap, and the cap can fill before the calendar date. The 2026 cap is 38,700 kW AC for Duke Energy Carolinas and 43,500 kW AC for Duke Energy Progress. Once a year's cap fills, new customers go to Residential Solar Choice even before January 1, 2027.
This is the part of the story to read carefully, because the numbers circulating online do not all describe the same program.
One widely quoted guide says Duke Energy Progress is full and Duke Energy Carolinas had less than 10% of its 30,000 kW left on September 24, 2026. That 30,000 kW figure is the combined size of a different program — Duke's PowerPair solar-plus-battery pilot, capped at 15,000 kW per rider pathway. PowerPair is a separate incentive (up to $9,000 for solar plus a battery, installed by a Duke-approved Trade Ally); its capacity is not the Bridge's capacity. The same guide notes elsewhere that Duke's site could not be reached in October or on November 18, so its Duke figures keep an earlier date. I am not repeating the "full" or "nearly full" claim as a Bridge fact, because I could not verify it against Duke's tariff or a Duke capacity page, and the figure behind it belongs to PowerPair.
What I could verify is this: no source I checked — including a careful October 2026 guide that read Duke's tariff — could confirm how much of the 2026 Bridge cap remains, and it advises asking Duke or your installer for that number in writing. Duke's own program pages publish no live remaining-capacity figure for the Bridge that I could find. So the accurate statement, as of November 18, 2026, is: the Bridge is open until December 31, 2026, while that year's room lasts, and the remaining room is unverified. If a salesperson tells you the exact room left, ask where the number came from and get it in writing from Duke. Do not read "unverified" as "plenty left" — a cap can fill fast in December, when every installer in the state is filing at once.
From January 1, 2027, a new Duke solar customer takes Residential Solar Choice. It requires a time-of-use rate with critical peak pricing, and it nets what you send to the grid against what you draw within each time-of-use period each month — critical peak hours are netted as their own period. Whatever is left over at month's end earns the same Net Excess Energy Credit as the Bridge: 4.53 cents per kWh in Carolinas, 3.94 cents in Progress.
The practical difference is the price of the power you buy. In Carolinas territory, the time-of-use schedule in force in August 2026 priced critical peak power at 42.7695 cents per kWh, on-peak at 23.4984 cents, off-peak at 10.2875 cents, and discount-period power at 7.4375 cents; in Progress territory, a November 2026 guide put the same periods at 41.002, 21.952, 11.000, and 8.274 cents. Treat those as the shape of the rate — very expensive at critical peak, cheap off-peak — not as a quote. Solar Choice also carries a $22 monthly minimum bill in Carolinas ($28 in Progress), a non-bypassable charge, and a Grid Access Fee of $2.05 per kW per month in Carolinas ($1.50 in Progress) on capacity above 15 kW. Systems are capped at 20 kW AC, or your home's estimated maximum monthly demand, whichever is less.
That is why a battery matters more under Solar Choice than under the Bridge: it moves midday solar into expensive evening windows instead of exporting it for about 4 cents. Start with our guide to sizing a battery for the loads you actually need before you price one in.
If you are on the original net metering rider (Rider NM), you have been on it since before it closed to new customers on September 30, 2023. You can stay on it until December 31, 2026, and then you will be moved to the Bridge rider or another rider in effect at the time. The move is automatic — the tariff says you "will be required to transfer" by January 1, 2027 — but which rider you land on, and what your last 12 months of bills would have been under it, are worth asking Duke about in writing. Your 15-year Bridge term, if you land on the Bridge, runs from your original interconnection application date. It does not restart when you are moved.
There is also a December 1 date in circulation, and it needs a careful label. One installer guide says that to choose the time-of-use option instead of the default move, you must opt in by calling Duke's Renewable Services Center by December 1, 2026. I could not confirm that date on Duke's tariff pages or the North Carolina Public Staff's net metering page, so treat it as reported by that guide, not as a Duke-confirmed deadline — and if you are on Rider NM and want the time-of-use rate, call Duke well before December 1 and get the answer in writing.
None of this applies if your bill is not from Duke. North Carolina's electric cooperatives and municipal utilities set their own net metering rules, and Dominion Energy North Carolina is a separate utility. Check whose name is on your bill first.
Any pitch that ties the December 31 Bridge deadline to a federal tax credit is mixing two different clocks. The 30% federal Residential Clean Energy Credit ended for expenditures after December 31, 2025, under the One Big Beautiful Bill Act. A system installed in 2026 gets no 25D credit, Bridge or no Bridge. On a lease or PPA, any business credit goes to the company that owns the system, not to you.

Bottom line: Duke's Bridge closes to new participants on January 1, 2027, and the filing date — not the contract date — is what gets you in, while the year's room lasts. The remaining room is unverified as of November 18, so the safe move is to file early, get the filing date and the rider name in writing, and have the same proposal priced on Solar Choice, which is where you land if the Bridge fills or the calendar turns.
This is general information, not tax or legal advice. Verify current program terms, eligibility, pricing, and the December 31 deadline with Duke Energy for your account before you register, sign, or file anything.
Sources: Duke Energy Carolinas Rider NMB, Fifth Revised Leaf No. 143, effective July 1, 2026, and Rider RSC, Fifth Revised Leaf No. 141, effective July 1, 2026 (via Solar Learning Lab, August 28, 2026, which links the Duke tariff leaves); North Carolina Utilities Commission order, Docket E-100, Sub 180, March 23, 2023; North Carolina Public Staff net metering overview; SolarDisclosure, "Duke Energy Net Metering Bridge Ends Dec 31, 2026," October 15, 2026; EcoGen America, North Carolina solar guide, updated October 19, 2026; Southern Energy, "Duke Energy Net Metering 2026," on the December 1 opt-in report; Cape Fear Energy / WilmingtonBiz, "How to Maximize Your Solar Power Savings in 2027," November 3, 2026, for Progress-territory time-of-use rates.